Below is a simplified case.
I have one node named comp01. And I have a Jenkins job named Compatibility.
Compatibility is scheduled as follows:
0 12 * * 1 %IntegrationNode=Software_1
0 17 * * 1 %IntegrationNode=Software_2
0 22 * * 1 %IntegrationNode=Software_3
0 2 * * 2 %IntegrationNode=Software_4
0 7 * * 2 %IntegrationNode=Software_5
The jobs start as scheduled. But sometimes, because of some verification failure, the previous job takes more than expected time. So, the next job starts before the completion of the previous job.
Is there a way available in Jenkins, in which the next scheduled job stays in a queue until previous job is complete? Or can we schedule based on previous job status?
We have tried limiting executors for this job, but when more than a couple of jobs are queued, then the expected behavior is not observed.
We have also tried by creating resource-groups and adding multiple nodes to it, but still, expected behavior is not observed when multiple jobs are in queue.
EDIT-1:
We can't use options { disableConcurrentBuilds() } since we start the job concurrently on different nodes. Here we are struggling to ensure that when a job is started on a node, then the other scheduled jobs for the same node should wait till the current job completes.

Have you tried setting the below option?
options { disableConcurrentBuilds() }
Update
AFAIK there is no OOB solution for your problem. But you can definitely implement something. Without seeing your actual Pipelines I can't give a concrete answer. But here ae some options.
Option 01
Use Lockable Resources and create a resource per Jenkins IntegrationNode and acquire it when running the Job, the next build will wait until the lock is released.
lock(resource: 'IntegrationNode1', skipIfLocked: false) {
echo "Run your logic"
}
Option 02
You can implement a waiting logic to check the status of the previous Build. Here is an sample Pipeline and possible Groovy code you can leverage.
pipeline {
agent any
stages {
stage('Build') {
steps {
script {
echo "Waiting"
def jobName = "JobA"
def buildNum = "92"
waitUntil { !isPending(jobName, buildNum) }
echo "Actual Run"
}
}
}
}
}
def isPending(def JobName, def buildNumber) {
def buildA = Jenkins.instance.getItemByFullName(JobName).getBuild(buildNumber)
return buildA.isInProgress()
}

Related

How do I lock a specific node in jenkins before executing a stage from Jenkins Pipeline script?

I have two nodes added in Jenkins,
- master
- node-1
Here is my pipeline script, I would like to lock all the executors on "node-1" before executing anything on "master"
node("master") {
stage("stage-1") {
// here lock node-1
//Execute script
}
}
Is there a way to achieve this? (ie: lock node-1)
My strategy is to mark the node offline as soon as your buyild job catches an executor, and then wait for all the other executors to complete. At this stage, your executor is still active, but the other executors can't get a new build since it's offline, so the node is all for yourself. When you are done, you can markl the node online again.
This requires some serious admin approval for the script.
For instance:
final int sleeptimeSeconds = 10
final String agentname = 'node-1'
echo "Waiting for an executor for ${agentname}..."
node(agentname) {
try {
timeout(time: timeoutminutes, unit: 'MINUTES') {
markAgentOnlineOfOffline(agentname, false)
sleep 5
Computer computer = Jenkins.getInstance().getComputer(agentname)
echo "Waiting for other executors to complete on ${agentname}..."
while (computer.countBusy() > 1) {
sleep sleeptimeSeconds
}
echo "Ready to do work on '${agentname}' in exclusive mode..."
...
}
} catch (e) {
markAgentOnlineOfOffline(agentname, true)
throw e
}
}
def markAgentOnlineOfOffline(String nodeName, boolean online) {
...
}
That last function markAgentOnlineOfOffline can be implemented in a logical (e.g. I use the "offline" label myself, which my jobs reject (li.e. the label requirement includes !offline). But you could use the Jenkins api to mark the node truly offline.

Jenkins build frequency based on previous build status

I have a Jenkins pipeline which is scheduled to trigger every 4 hours. However, my requirements is that once the build fails, I want the builds to happen more frequently and keep sending constant reminders that the build is broken. In short, the build schedule must depend on the status of the previous build.
Is that possible in Jenkins?
Thanks,
In Scripted Pipeline, you can do something like this :
def triggers = []
if(currentBuild.getPreviousBuild().result != 'SUCCESS') {
triggers << cron('0 */1 * * *') // every hour
} else {
triggers << cron('0 */4 * * *') // every 4 hours
}
properties ([
pipelineTriggers(triggers)
])
node {
...
}
I can't think of a direct way but you can have a workaround. You can have a replica of the same job(let's call it job 'B') and trigger it when the build of the first job fails(let's call it job 'A'). Now if B fails again then you can retrigger it(B) (adding some wait time) and send a notification after it fails, keep doing it until it passes. This will be done in a much easier way if you are using the scripted Jenkins pipeline. Hope this answer helps you in some way.

Cron job executing in Jenkins DSL

I am trying to create a cron job which run some smoke tests every 10 minutes, my seedjob looks like this :
multiBranchJobs.each { currentJob ->
multibranchPipelineJob(currentJob.name) {
branchSources {
git {
remote(currentJob.projectGitUrl)
credentialsId(currentJob.credentials)
includes(currentJob.includes)
}
}
orphanedItemStrategy {
discardOldItems {
numToKeep(20)
}
}
triggers {
cron "H/5 * * * *"
periodic 60
}
}
}
the problem with the current approach is that it will get executes only if it detects changes in the SCM, which is not the case for the smoke tests. I need to run it every 5 minutes regardless of commits in source control. Any clue ?
I'm not entirely sure how to solve your problem, but I think the cron trigger you have is not doing what you think it is. I THINK this will set this trigger on the multibranch indexing job itself. In the UI that is not even an option. Apparently it isn't throwing an error, but I have to wonder if it is actually setting the trigger.
The jobs that get created from the multibranch job must have a Jenkinsfile, right? You can set the triggers in those Jenkinsfiles.
I haven't built jobs using code, so take that into consideration when you review my answer. But it SEEMS to me that you are setting the trigger in the wrong place.

Jenkins pipeline milestone not cancelling previous ongoing build

I am experimenting with Jenkins pipeline and milestones and cannot figure out why Jenkins is not cancelling the previous build when a new build crosses the milestone.
Example Jenkinsfile
pipeline {
agent any
parameters {
booleanParam(defaultValue: true, description: '', name: 'userFlag')
}
stages {
stage("foo") {
steps {
milestone(ordinal: 1, label: "BUILD_START_MILESTONE")
sh 'sleep 1000'
}
}
}
}
Triggering this pipeline twice does not cancel the 1st job
Try this:
/* This method should be added to your Jenkinsfile and called at the very beginning of the build*/
#NonCPS
def cancelPreviousBuilds() {
def jobName = env.JOB_NAME
def buildNumber = env.BUILD_NUMBER.toInteger()
/* Get job name */
def currentJob = Jenkins.instance.getItemByFullName(jobName)
/* Iterating over the builds for specific job */
for (def build : currentJob.builds) {
/* If there is a build that is currently running and it's not current build */
if (build.isBuilding() && build.number.toInteger() != buildNumber) {
/* Than stopping it */
build.doStop()
}
}
}
I don't think the behavior is "If I'm a newer build that crosses this milestone, then all older build that crossed this milestone will be cancelled"
The actual behavior of the milestone step is that when a more recent pipeline crosses it first, then it prevents older pipeline from crossing that milestone.
I have a simple work around with milestone plugin, according to the document:
Builds pass milestones in order (taking the build number as sorter field).
Older builds will not proceed (they are aborted) if a newer one already passed the milestone.
When a build passes a milestone, any older build that passed the previous milestone but not this one is aborted.
Once a build passes the milestone, it will never be aborted by a newer build that didn't pass the milestone yet.
you can try something like this:
pipeline {
agent any
stages {
stage('Stop Old Build') {
steps {
milestone label: '', ordinal: Integer.parseInt(env.BUILD_ID) - 1
milestone label: '', ordinal: Integer.parseInt(env.BUILD_ID)
}
}
}
}
you can put this at the start of any pipeline.
Assume you just start a new build, #5. The first milestone, will be used to passes #4's second milestone, and the second milestone(of #5) will be used to kill #4's process, if it's currently running.
The disableConcurrentBuilds property has been added to Pipeline. The Pipeline syntax snippet generator offers the following syntax hint:
properties([disableConcurrentBuilds(abortPrevious: true)])
That property is used on ci.jenkins.io to cancel older plugin build jobs when newer plugin build jobs start.
Declarative Pipeline also includes the disableConcurrentBuilds option that is documented in the Pipeline syntax page.
The declarative directive generator suggests the following:
options {
disableConcurrentBuilds abortPrevious: true
}
as per https://jenkins.io/blog/2016/10/16/stage-lock-milestone/, a pair of 'milestone()' works for me to kill the previous jobs while the pipeline kicked off for times,
stage('Build') {
// The first milestone step starts tracking concurrent build order
milestone()
node {
echo "Building"
}}
// The Deploy stage does not limit concurrency but requires manual input
// from a user. Several builds might reach this step waiting for input.
// When a user promotes a specific build all preceding builds are aborted,
// ensuring that the latest code is always deployed.
stage('Deploy') {
timeout(time: 60, unit: 'SECONDS') {input "Deploy?"}
milestone()
node {
echo "Deploying"
}
}
The last milestone helps kill previous builds if reached, say deploy button clicked for the above case. Or the locked resource released for the below case,
// This locked resource contains both Test stages as a single concurrency Unit.
// Only 1 concurrent build is allowed to utilize the test resources at a time.
// Newer builds are pulled off the queue first. When a build reaches the
// milestone at the end of the lock, all jobs started prior to the current
// build that are still waiting for the lock will be aborted
lock(resource: 'myResource', inversePrecedence: true){
node('test') {
stage('Unit Tests') {
echo "Unit Tests"
}
stage('System Tests') {
echo "System Tests"
}
}
milestone()
}
Building on #D.W.'s answer, i found a simple pattern that works. It seems to fit into D.W.'s bullet #3 (which is the official doc): When a build passes a milestone, Jenkins aborts older builds that passed the previous milestone but not this one.
Adding an earlier milestone that everything will pass, and then one after the thing that is going to wait, makes it all work like you think it should. In my case:
steps {
milestone 1
input 'ok'
milestone 2
}
Create two active builds with this, and only approve the second one. You'll see the first one get automatically canceled, because build 2 passed milestone 2 first.
Try taking out milestone 1, and you'll see that build 1 does not get canceled when build 2 passes milestone 2.
Adding the early milestone satisfies the requirement. It seems that a build has to pass any milestone before a future milestone passed by a newer build will cause it to cancel.

Jenkins Pipeline and semaphores

I'm building a Jenkins job that will run all my staging tests continuously, but not all at once (they rely on shared hardware). So, I'm creating parallel jobs, with a semaphore to ensure that only a limited amount are run at once.
Here's a simplified version of my pipeline that reproduces the issue:
import java.util.concurrent.Semaphore
def run(job) {
return {
this.limiter.acquire();
try {
println "running ${job}"
build job
println "finished ${job}"
} finally {
this.limiter.release();
}
}
}
def getJobs() {
def allJobs = Jenkins.getInstance().getJobNames()
def stagingJobs = []
for(String job : allJobs) {
if (job.startsWith("staging/temp")) {
stagingJobs.add(job)
}
}
println "${stagingJobs.size()} jobs were found."
return stagingJobs
}
this.limiter = new Semaphore(2)
def jobs = [:]
for (job in getJobs()) {
jobs[job] = run(job)
}
parallel jobs
When I run without the semaphores, everything works fine. But with the code above, I get nothing outputted except:
[Pipeline] echo
6 jobs were found.
[Pipeline] parallel
[Pipeline] [staging/temp1] { (Branch: staging/temp1)
[Pipeline] [staging/temp2] { (Branch: staging/temp2)
[Pipeline] [staging/temp3] { (Branch: staging/temp3)
[Pipeline] [staging/temp4] { (Branch: staging/temp4)
[Pipeline] [staging/temp5] { (Branch: staging/temp5)
[Pipeline] [staging/temp6] { (Branch: staging/temp6)
If I view the pipeline steps, I can see the first two jobs start, and their log messages output. However, it seems like the runner never receives a notification that the staging jobs finish. As a result, the semaphore never releases and the other 4 jobs never manage to start. Here's a thread dump mid test, after the downstream builds have definitely finished:
Thread #7
at DSL.build(unsure what happened to downstream build)
at WorkflowScript.run(WorkflowScript:9)
at DSL.parallel(Native Method)
at WorkflowScript.run(WorkflowScript:38)
Thread #8
at DSL.build(unsure what happened to downstream build)
at WorkflowScript.run(WorkflowScript:9)
Thread #11
at WorkflowScript.run(WorkflowScript:6)
Thread #12
at WorkflowScript.run(WorkflowScript:6)
Eventually it times out with several java.lang.InterruptedException errors.
Is it possible to use semaphores in a pipeline, or is there a better way to ensure only a portion of jobs run at once? I would rather avoid spinning up nodes for what amounts to a simple test runner.
The Concurrent Step plugin was just released and should work nicely for this use case.
Wtih this, you can simplify your code:
def semaphore = createSemaphore permit:2
def run(job) {
return {
acquireSemaphore (semaphore) {
println "running ${job}"
build job
println "finished ${job}"
}
}
}
...
Possible workaround with lock step
Lockable resources plugin has no semaphore capabilities.
It took me a long time to figure out how to squeeze the lock step into semaphore behavior... it would be nice if it could do it on its own. Here's an example...
int concurrency = 3
List colors = ['red', 'orange', 'yellow', 'green', 'blue', 'indigo', 'violet']
Map tasks = [failFast: false]
for(int i=0; i<colors.size(); i++) {
String color = colors[i]
int lock_id = i % concurrency
tasks["Code ${color}"] = { ->
stage("Code ${color}") {
lock("color-lock-${lock_id}") {
echo "This color is ${color}"
sleep 30
}
}
}
}
// execute the tasks in parallel with concurrency limits
stage("Rainbow") {
parallel(tasks)
}
The above will create custom locks:
color-lock-0
color-lock-1
color-lock-2
The all concurrent tasks will race for one of the three locks. It's not perfectly efficient (certainly not as efficient as a real semaphore) but it does a good enough job...
Hopefully that helps others.
Limitations
Your pipeline will take as long as your slowest locks. So if you unfortunately have several long running jobs racing for the same lock (e.g. color-lock-1), then your pipeline could be longer than if it were a proper semaphore.
Example,
color-lock-0 takes 20 seconds to cycle through all jobs.
color-lock-1 takes 30 minutes to cycle through all jobs.
color-lock-2 takes 2 minutes to cycle through all jobs.
Then your job will take 30 minutes to run... where as with a true semaphore it would have been much faster because the longer running jobs would take the next available lock in the semaphore rather than be blocked.
Better than nothing; it's what I have so far. Sounds like a good time to open a feature request with the lockable resources plugin.
Since at least a year there's a plugin which will help you to get what you intent and there's also the option to use this plugin in pipeline jobs, the plugin is Lockable Plugin Resource
Basically you wrap your share resource and the job will queue before the lock statement if the resource is not free.
If you are interested in parallelizing your tests you also can have a look at the Parallel Test Executor Plugin

Resources