In TFS2015 I have 2 branches:
Main & Release
Main contains development code and developers are required to merge Main into Release.
We've had a couple of instances recently where devs have not bothered getting latest of Release before performing their merge from Main to Release. This has caused a few headaches as bodged merges have gone in.
Does anyone know of any automated policies that could be put into place that would stop a merge to the target branch unless the dev has the latest version downloaded.
Thanks

No such an existing policy to restrict the merge. You need to write your own policy if possible. There is a sample for your reference: Merge / Branch Only Check in Policy
Another workaround is creating a script with tf get command to get latest version, then auto run the script periodically, thus the local version will always be the latest version. See below articles to set the auto run task:
How to schedule a Batch File to run automatically in Windows
10/8/7
Run a task every x-minutes with Windows Task Scheduler

Related

Can a TFS2015 script only Deploy (and not Build)?

I am new to the world of scripting with TFS2015. I created a script that builds all of the projects within my solution (it is a rather large solution) and puts it out in a shared folder (where each project has its own subfolder).
I would like to create a separate script for each project that simply copies the bin folder from the shared and pastes it out on my Test environment. I rarely need to deploy everything, so the idea is one build...multiple deploys.
However, when I run my deploy script using the Copy Files step it is doing another build. Although it copies the files that I expect, it is after a full build that creates the folder structure for the build.
Am I able to make the Copy Files step NOT do a Build?
Here is the steps that my script is curently doing:
As you can see, there is only one step (Copy Files) but it still does the Get sources and copies everything into a new folder on the build box like so (where the number keeps incrementing up with each run of the script):
I just want to copy the files from the Source to the Target and not do a build or Get Sources.
It looks like you're still on TFS 2015 RTM or Update 1. Which is already pretty old technology if you compare it to the lifetime of the new build system which was introduced with this version.
TFS 2015 update 2 has introduced a similar system to the Build pipelines to orchestrate Releases. This doesn't require you to map any workspaces or git repositories and can act on the artefacts of your builds or simply on the contents of file shares.
It makes sense that a Build has to build something and in order to build something, it has to get the things to build. If you're actually not building something, then you're probably deploying or releasing or packaging something else. Hence the distinction between Build and Release pipelines.
TFS 2017+ has an option to disable the syncing of sources. Primarily to allow people to get the sources themselves in creative ways (e.g. a custom powershell script that invokes git.exe).
My primary advice would be to upgrade to TFS 2018 update 3 or at least TFS 2017 update 3.1, worst case TFS 2015 update 4.1. The fact that versions older than update 2015.4.1 have a known XSS scripting security bug may be reason enough to convince your organisation to perform this update.
Barring that option you're left with one solution:
Link your build definition either to a git repository with only a single commit (If I remember correctly the 2015 agent still crashes when syncing an empty Git repo) or link it to a TFVC repository and set the workspace settings to cloak everything. This essentially causes the build to sync an empty folder, which it can cache, before calling your powershell script.

Commit file back to repository from build server in Visual Studio Team Services

I'm currently setting up continuous integration using TFS/Visual Studio Team Services (was VS Online), and I'm using the Team Foundation Build 2015 tasks. So not the XAML builds.
I'm using it to build a Xamarin Android project, but that's pretty irreverent I guess,
The process should be like this:
After a check-in:
TFS should download the sources
TFS should increment the version number within AndroidManifest.xml
I've managed to do this by making a PowerShell script for this.
After the AndroidManifest.xml file is modified, it should be committed back into the TFS repository
Then the rest, build deploy into hockeyapp etc
The first steps are all configured, but I'm struggling with the commit part. How do I get TFS to commit the file? I don't really see any task suitable for it. I've tried using the Copy and Publish Build Artifacts Utility - But that did not seem to work, and I'm not even sure if that's the right utility
I'm using the default hosted build agent btw. Any help would be appreciated
Warning
I do want to point out that checking in changes as part of the build can lead to some features of VSTS/TFS not working. Association of work items to the checkin, sources and symbol generation, tractability from changes to build to release and integration with Test Manager, remote debugging, will likely not yield the expected results because the Changeset/commit recorded in te build may not match the actual sources. This may lead to unexpected funny behavior.
Also, if any new changes have already been committed/checked-in after the build has started, the version number may be updated in Source Control for code that was not actually released under that version.
So: First of all, it's considered a bad practice to change the sources from the build process.
Alternatives
There are better ways of doing it, one is to use the build version (Build_BuildNumber or Build_BuildID variables). Alternatively you an use a task like GitVersion to generate the semantic version based on the branch and tag in your git repository. That way your build will generate the correct version number and will increment the revision in case the same sources are built multiple times.
I understand, but I still want to check in my code as part of the build
If these things don't work for you and you still want to check in the changes as part of the build, you can either use the TFVC Build Tasks if you're using TFVC or use the Git Build Tools to add the remote to the local repository and then use the git commandline tools to commit and push the changes back to the repository.
These extensions require TFS Update 2 to install. But you can push the individual build tasks using the tfx commandlien tool. For the TFVC tasks the process is explained here.
On mac
On the mac it's going to be harder since you're using TFVC. My TFVC tasks leverage the TFS Client Object Model and Powershell to communicate to the TFS Server. The tf.exe tool doesn't even work on windows when you're in the context of a build, which is why I need to call into the VersionControlServer object directly. Given I'm dependent on these technologies, the tasks won't run on a Mac or Linux agent.
You could try to see whether the Team explorer Everywhere X-platform commandline works from the build agent (using a shell script). I have no way to test this on an actual Mac.
Given the cross platform nature of your project I'd recommend to move to Git, it integrates into XCode and Android Studio, making it easier to do a native UI or build on top of native libraries.
Alternative 2
You could setup a build which does the required changes to the code and then checks in the modified code. Then have a (CI) build run the Android and the Mac builds using the modified code.

TFS2012 - Manifest of multiple folders with different versions

I'm new to version control systems and have been tasked with revamping our company's version control (small system right now). We have library files that will get updated, but we also need to support older versions of these libraries for different generations of our product. Part of my task is to set up an automated unit testing system that will do nightly checkouts, if newer code has been checked in since the last test run.
You will likely need to keep multiple branches of your libraries in source control, one for each version that will be supported/changed in the future. Each of these branches should have a build definition created to build the code and then run the unit tests against the code. The builds can be setup to run in
CI mode which will build on every checkin
Gated checkin mode (my personal favorite) which won't commit the checkin until the build and test run completes successfully.

Execute a build in TFS based on a previous build

We're using TFS to follow a pretty standard agile build process:
Nightly builds from latest source code
Build to staging server every 2 weeks
Build to production server every 4 weeks
I've got 1 and 2 set up in TFS and working great. However, I'm struggling a little with #3. If I just set up a "normal" build, it will pull the most recent source code and use that to push to the production server. But what I really want is to move the code from step #2 to the production server since it's already been vetted by the QA team.
I thought about doing a custom build template that uses XCopy or something along those lines, but then the issue is how to update the configuration strings.
I was following this article, which seems to be exaclty what I want, http://www.asp.net/web-forms/tutorials/deployment/configuring-team-foundation-server-for-web-deployment/deploying-a-specific-build, but it is not working.
How do you all accomplish this?
So this is a slightly easier way to achieve 3. if you have achieved 2.
Let your production build definition stay as it is. However to compile the same changeset that was used to compile your staging build in step 2 (which has now been vetted by QA), when you queue a prod build then on the parameters tab expand the Advanced section and find the "Get Version" property as shown below.
In here you can specify the same TFS changeset that was used to build your build in step 2. Assuming this changeset is number 84, you would write (exactly)
C84
if you compile labels then for a label named - "For build xyz" you specify
LFor build xyz
Note that "C" and "L" above are intentional.
Hope this helps.
We have a different branch for production and code only gets merged into the production branch after passing Q&A.
That allows us to apply hot-fixes to production code with changes directly on the production branch (those will eventually get reverse integrated into main then dev) while development continues on the development branches.
Once code in the development branches are ready for Q&A, it is merged into the Main trunk.
CI and nightly builds are done on the development branches - the difference being nightly builds having more comprehensive automated tests

TFS 2008 Continuous integration MSBUILD on Branch fails on Label

I am attempting to use CI on a Branch of one of my TFS projects. MSBuild only fails when I try to use a Branch. I point the same Build at the "trunk" project it works fine.
The error I receive from the build log:
Task "Label"
Label TeamFoundationServerUrl="http://TFSServer:8080/"
BuildUri="vstfs:///Build/Build/6763"
Name="Test_SF_20090619.1"
Scope="$/MyProject" Recursive=True
Comments="Label created by Team Build"
Version="BuildServer3D143_66"
Child="Replace" Files="$/" C:\Program
Files\MSBuild\Microsoft\VisualStudio\TeamBuild\Microsoft.TeamFoundation.Build.targets(812,5,812,5):
error : No matching items found in $/
in your workspace.
Done executing task "Label" -- FAILED.
Done building target "CoreLabel" in project
"TFSBuild.proj" -- FAILED.
I believe this error is being caused by a lack of source files getting copied to the Build server.
Get task excerpt from build log:
Task "Get"
Get TeamFoundationServerUrl="http://TFSServer:8080/"
BuildUri="vstfs:///Build/Build/6768"
Force=True Overwrite=False
PopulateOutput=False Preview=False
Recursive=True Version="C204806"
Workspace="BuildServer3D143_66"
Done executing task "Get".
This is a full build. There should be about a thousand files listed in the GET.
General Information
TFS 2008
Visual Studio 2008
Established build server (been
running builds for the last year)
Project being branched is a ASP.NET
web stie (2.0 Framework).
Full Build Params
/p:SkipClean=false
/p:SkipInitializeWorkspace=false
/p:ForceGet=true
/p:IncrementalBuild=false
/p:IncrementalGet=false
note: I know IncrementalBuild is redundent but I just wanted to be sure.
Questions:
Are there restrictions on builds off a branch?
Any idea why MSBuild fails to pull files from the branch workspace?
If it's for CI then you're most likely doing an Incremental Get. TFS will only bother to get files it thinks have changed since its last get - e.g. if you delete any files from your server, it will still think you have those files so it won't get them again. In this case you'll need to run the build once with the incremental properties turned off so that it forces a full get of the source. You can do this by overriding the properties in the MSBuild command line box in the Queue Build dialog with:
/p:IncrementalGet=false;ForceGet=true
Another possibility that springs to mind is that the Label task is confused by your branch. It may be that your workspace is set up incorrectly, so check that you're mapping in everything it needs.
I had two issues in this case.
First, the branch security did not give rights to the build service account. I had restricted the branch to our team's Tech Leads and Release Engineers. The build service account needed access as well. What tipped me of was while searching the internet I stumbled upon a posting by someone who had made the same mistake.
The second issue was a little more involved. While cleaning up my build project file, I removed the following section.
<SolutionToBuild Include="$(BuildProjectFolderPath)/../../_stage/MyProject/MySolution.sln">
<Targets></Targets>
<Properties></Properties>
</SolutionToBuild>
Which worked fine on projects I had already built at least once, but if this was a new build, that had not copied source files to the build server, then there would be no files and the build would fail.
Some of you may wonder if my other builds were working either, after all wouldn’t they have old build files. Yes, but I had targets defined that did all the work I actually cared about. So the SolutionToBuild is a little frivalous.