How do I schedule dependent jobs in Jenkins. I cant schedule it as 1st week , 2nd week or 3rd week to maintain the number of runs. We want the schedule weekly.
Job1 to run on week1
Job2 to run on week2
Job3 to run on week3
Again,
Job1 to run on week4
Job2 to run on week5
Job3 to run on week6.
And the schedule goes on ..
How do I script this in Jenkins "Build Periodically".
Thanks in advance.
I don't think you could do this with a cron expression. I think the best you could do is setup a weekly job and then use logic to execute the appropriate build.
You could either use a pipeline job, the conditional build step plugin, or if you really need them to be entirely separate jobs, build a pipeline job that runs weekly, decides which job to run, and then kicks off the appropriate job using the "build" step. You have much more powerful logic available to you this way, instead of just a cron expression.
This is the format to schedule jobs Weekly and Monthly
MINUTE (0-59), HOUR (0-23), DAY (1-31), MONTH (1-12), DAY OF THE WEEK (0-6)
Weekday daily build twice a day, at lunchtime 12:00 and midnight 00:00, Sunday to Thursday: 00 0,12 * * 0-4
Every first of every month between 2:00 a.m. - 02:30 a.m.: H(0,30) 02 01 * *
Related
We work on a product whose software development team applies patch on every 1st Friday of the month. We have written some tests that we run on the Sunday after the patch is applied. So to automate the same on Jenkins, we would need a cron that runs on 1st Sunday after the 1st Friday of the month has passed.
Right now we just update our Jenkins each month considering dates, but can we automate this?
Thanks
Naively, one would suppose that 0 3 1-7 * fri would be "3am on the Friday that falls inside the first week of each month", and then we could use the similar logic to construct 0 3 3-9 * sun, for the Sunday that follows two days after such a Friday.
Unfortunately, this does not work, because day of week and day of month are taken as a disjunction by the cron specification; which means, the above would trigger not on the Sunday following the first Friday in a month, but on every Sunday, and also every day from 3rd to 9th.
Due to this twist in cron spec, what you ask is not possible by cron alone. The easiest way to untangle this is to separate the two requirements, ask the cron to track one of them, and manually test the other: either use 0 3 3-9 * * and then manually test in your script whether the day is Sunday and exit without performing your task if it is not, or use 0 3 * * sun and manually make sure the date is between 3rd and 9th.
I have a job that is configured to schedule and run a job periodically using the following schedule:
01 14 * * 1-5
For some reason, the job is triggering twice every day at the same time. I cannot work out why it is triggering twice. I suspect two possible issues:
The Day of Month (DOM) and Day of Week (DOW) is contradicting
The fact that there are multiple spaces after each column might be confusing Jenkins
Questions
Am i correct that the above says the job should run daily at 14:01 UTC?
What is the significance of the last field? If the fourth field (day of month) specifies * meaning every day of the month, what would be the purpose of the last field (Day of Week)?
What would be the behaviour if i had something like this (where DOM and DOW contradict)
01 14 * * 5
I have created my job and want to trigger build daily at 11am and in any other time I should not be able to trigger it.
You can Go to “Build Triggers” section in jenkins and under that Check “Poll SCM”, here you can create cron jon for your pipeline trigger.
For you query you can give somethind like below in the Poll SCM schedule box:
0 11 * * *
Jenkins used a cron expression, and the different fields are:
MINUTES Minutes in one hour (0-59)
HOURS Hours in one day (0-23)
DAYMONTH Day in a month (1-31)
MONTH Month in a year (1-12)
DAYWEEK Day of the week (0-7) where 0 and 7 are sunday
For more info please visit here
To add on the given answer , you can also add a simple bash script to check the time and exit or do the same in the jenkins pipeline
I am trying to schedule a jenkins job (timer) to start my Azure VMs back up on the third sunday of every month at 6AM.
I haven't been able to find any resource on this.
From Configure job, You can use Build Periodically option
under Build Trigger section and in the Schedule text field add the expression: 0 0 1 * *
The above expression will schedule a build of the job to run on 1st day of every month. For example, Would last have run at Monday, October 1, 2018 12:00:55 AM EDT; would next run at Thursday, November 1, 2018 12:00:55 AM EDT and so on. To create your own cron based upon your requirement you can use https://crontab.guru/.
I have a Jenkins job that runs every day at 8:30 AM.
I want the job not to run on Fridays. Is there a way to achieve this ?
You can use the dow (day of week) to achieve it:
30 8 * * 0-4,6 your_command
# 0=Sunday 6=Saturday