I'm using TFS 2015 on-prem and I'm using the standard SCRUM template. I have 1 Team Project and I'm using the team field to segregate work. I have created a few build definitions and ran a few builds over the last few weeks.
When I installed TFS I did not install or configure Reporting Services straight away as I had planned to do that later. I have since done this and I now have my Tfs_Warehouse which is updating with most things but NOT FactBuildProject or FactBuildDetails. Some of my other facts are pulling over, such as FactCurrentWorkItem and even FactBuildCoverage. I have rebuilt the warehouse in the TFS Admin Console.
As this is a standard process template and standard reports I expect that the required fields should be set to reportable.
How can I get data in my FactBuildProject table and where can I look for issues with it? I'm not sure where to start and I can't find anyone else in the world with a similar problem.
If you are using the new task-based build system, then you are out of luck, since that data is not being propagated to the data warehouse.
Check the comments on this blogpost: http://nakedalm.com/create-a-build-vnext-build-definition-on-vso/
Related
I have been responsible for administrate our TFS projects and have started to investigate the current configurations. I found the following link for determining which process our team projects are connected to: How to determine what Process template an existing TFS 2012 project is configured with?
When using the rest API described in the article above, it seems like the projects depend on a process template called "Microsoft Visual Studio Scrum 2013". When reading this article: Scrum process it seems to me that the process is outdated and should be upgraded to use the "Scrum" template.
I have searched the internet for knowledge on how to upgrade the project to use the new Scrum process but had no luck of finding an answer. Does anyone have an idea of how to update the projects to depend on a newer process? Maybe the whole question is wrongly put as I may lack some obvious knowledge about how these things are meant to work. All I want is to ensure our projects are updated to use the latest TFS technology.
We use Visual Studio 2017 and did recently upgrade our TFS server to TFS 2018.
In general, some new features will be introduced when upgrade from old to new version of TFS.
Generally if you haven't made any changes to the original process template, upgrading is quite easy. Just enable new features by running the Configure Features Wizard in your team projects configuration page.
If it can’t upgrade automatically, you need to apply updates manually. See Add updates to team projects manually.
If you customized the process template, then you can follow the steps mentioned in this link to Update a customized process template to access new features.
To update the existing projects, a not so nice but easy way is to remove all work items and process data from your project and then add the newest items. Martin Hinshelwood has some great guidance on how to do this.
I assumed this would be easy, but I'm not finding anything on it...
I have a project in TFS 2010, which needs to be moved to a new TFS 2015 server. Apparently the project cannot simply be moved normally because it's using a different project template which is not compatible and causes errors when trying to migrate (so I'm told - I don't have any more details on this).
I'm looking for a way to bring over the changesets, keeping history, to the new server. I assumed there was some kind of "dump" where you could export the TFS changesets, then import them into the new server into an empty project - but I'm not finding that option.
TFS Integration is deprecated and apparently doesn't work for TFS2015, with no alternative listed.
I'm open to other creative options like temporarily exporting to a different version control system - for example, I've looked at SVNBridge, but I can't even get that working, let alone figure out if it would help here.
Is there a way to migrate all changesets for a given project and keep history, without migrating the entire project?
There is no default way to migrate changesets in TFS, you would need 3rd party tool, like OpsHub (some features are not free), to migrate the most commonly requested data. Check: http://www.opshub.com/products/opshub-visual-studio-migration-utility/
Or you may consider doing a upgrade from TFS 2010 to TFS 2015, which is a full data transfer. To understand factors that affect your upgrade's compexity, check the requirements and review the upgrade process.
Learn if a dry run makes sense for you, and weigh the benefits and the costs to perform a pre-production upgrade.
When you're ready to upgrade, minimize downtime with the TfsPreUpgrade tool - especially for very large TFS collection databases (> 1 TB). Follow these steps for how to upgrade TFS.
I am currently trying to solve an issue with our current on-premise TFS 2010 Server where I have 2 collections and both of my project collections were set to offline due to some tinkering with trying to upgrade to on-premise TFS 2015.
Whenever I try to activate the desired collection, I am getting the following error:
TF253021:The following team project is duplicated in at least two team
project collections: ProjectName. The collection cannot start while
the duplication exists. You must delete this project from all but one
of the collections before the collection can be started. The project
exists in the following collections: CollectionA, CollectionB.
I also had a look at each of their settings, and apparently the database connection string for both collections are pointing towards the same SQL Server instance and the same database. Both collections also have the same number and names of all team projects too.
I'm thinking of deleting one of the collection and its projects, but I fear that if I do it, it may delete the same collection and settings for the second project collection that I'm trying to set online.
I'm wondering if anybody has encountered this issue and what steps have he/she has done to fix it.
Many thanks!
You've gotten yourself in a remarkable situation, which may need Microsoft support to chime in. Even with creative backups I'd be unsure whether you'd get yourself in an unsupported end-situation.
If you have a backup of the whole situation before you started this experiment, I'd recommend going back to that.
You may find yourself in a catch-22 situation, since TFS 2010 has passed it's support lifecycle. Mentioning it happened while preparing for a TFS 2015 upgrade may convince them.
You can find the contact details here:
https://support.microsoft.com/en-us/contactus/
I am working on a TFS Implementation where the original Project that was created has a cpace in the name. This is causing issue in our builds since we need to kick off a batch file for the Deploy process and the space in the name creates some issues with the path name of the build folder. With this, I want to create a new project without the space. As you can imagine, I would like to keep the revision history of the Source Code if possible.
I have looked at this StackOverflow
Team Foundation Server - Moving Source with History
But I am a bit confused about what I would need to do. Is there someone out there that can point me to a document that is more friendly to someone who doesn't have a lot of TFS experience.
We've been faced with a similar task and we've used the TFS Integration Platform which might be of use to you.
Here's a couple of good blog posts on how to use it:
TFS Integration Tools - Part 1
TFS Integration Tools - Part 2
Last week I upgraded our TFS 2012 Server to TFS 2013. I read the MSDN documentation first and I also followed the documentation as I performed the upgrade. Everything seemed to go ok.
After the upgrade I ended up with 7 or so Team Projects that the wizard couldn't configure, for whatever reason, and needed manual configuration.
I noticed this week that ALL of the work items under one of my Team Projects are missing. Gone. Like even if I select Team|Go To Work Item and enter in a known Work Item Id, I receive an error that the item is either missing or I do not have permission to view it. I'm an Administrator on the TFS server and I'm the TFS Admin, so I highly doubt permissions are the issue.
I remoted into the server and launched SSMS to explore the raw data. I know for a fact Work Item 450 is missing (it's the only Id I remember at this point). I selected the TOP 1000 from WorkItemsAre, which seems to be the table that holds the Work Items (?). There is a gap in the Ids, I see 1-448, then the numbering picks up again at 457. So, somehow my Work Items appear to have been deleted. I stopped there, I assume there are more gaps since I'm missing more than 9 items.
Now I haven't gone through every one of our Team Projects. I've only touched 3 of them since the upgrade. Thankfully the largest, most active Team Project, with the most work items/version history seems to be intact. I'm not sure if any other Team Projects are missing their Work Items too.
Has anyone else experienced this? Does anyone know if there's some "secret squirrel" way to recover these missing work items, or have they been hard deleted and are gone for good (other than looking through tape backups of the server).
Any advice would be appreciated.
I already migrated to TFS 2013 from TFS 2012.
The problem of manual configuring the project may occur when you have customized work item types in TFS Project Templates. Did you customize your project templates?
Although, I can hardly believe that work-items getting hard deleted from TFS. This issue may occur probably because of archiving during migration. The workitems that TFS upgrade wizard may not have "understood" during migration/upgrade, might be archived and moved to another table in database Tfs_DefaultCollection.
You may want to consider that. I am not sure if that may be the case, but this happened when we migrated from TFS 2010 to TFS 2012 because we had many custom work items in TFS 2010. Hence we had to standardize templates before migration using powershell. But we lost some amount of history.
Hope that sparks some idea.